The project documentation was developed to define all system characteristics and performance and to detail every activity required to carry out the revamping of Primary Substation 116064 at the Porto Torres site.
The new electrical system included the following switchboards:
A key aspect of the design was the definition of the high-speed Automatic Transfer System (ATS-HS), ensuring service continuity depending on fault type and the 6 kV MV network configuration. For all MV and LV protections, a redundant Ethernet network via optical fiber was adopted using IEC 61850 protocol.