Insertion of compressors C.le Gas Ravenna (RA)

Activity details

DESIGN OF 15 AND 6KV MT NETWORKS FOR COMPRESSOR POWER SUPPLY

The project documentation was developed in order to define all the characteristics and performances of the 6KV starting system of the two new compressors of the C.le Gas Eni di Rubicone. The problems solved were those of starting two 2700KW/each motors without producing dangerous disturbances on the 15KV network of the distribution company (ENEL). In addition to the electrical design, the 6KV Inverter containment cabinet and that of the auxiliary transformer were also defined in terms of construction.

Activities
Construction engineering insertion of gas compressors.

Subject
Gas Plant di Rubicone New Compression, The plant is mainly composed of the following systems:
  • MV Panel 15KV
  • MV Panel 6KV
  • Transformer MV/LV 15/0,4KV 400KVA (aux)
  • Transformer MV/LV 15/6KV 3600KVA
  • Inverter 6KV (Soft-Start)
  • Power factor correction panel 6KV 2x750KVAR
  • Inverter/Transformer Cabins

Total hours: 4500