The project consisted in modifying the substation configuration by introducing a by-pass, enabling maintenance activities on the 132 kV substation (SSE) while maintaining operation.
The new high-voltage circuit breaker (ABB PASS) is connected on the incoming side to a cable line derived from the utility delivery point. On the outgoing side, the breaker feeds Transformer 2 (HV/MV), thus allowing maintenance with continuity of service.
The designed works included: